Pre-opening Planning for 460-bed Hotel in Krakow

Project Description

Meininger Krakow Pre-opening Licensing – Phase 2 

Project Type

Pre-opening Planning 

Country

Poland

The Client

A hospitality company that was founded in Berlin in 1999 and operates in 25 European cities. The company offers hybrid hotels which combine the comfort of a hotel with the vibe of a hostel, offering affordable rates, high-quality amenities, and central locations. 

Background 

The client was in the process of opening the 460-bed hotel in Krakow, Poland. 

Client Need 

In November 2022, the client commissioned HSP to conduct research and compile a list of all the certificates, approvals and accreditations needed to open and operate the hotel (Phase 1).  

Following delivery of the report, the client requested help obtaining between 9 and 11 of the necessary certificates and approvals that were listed in the Phase 1 report. The client also required support for the hotel’s opening general manager, and departmental heads on an ad hoc basis throughout the pre-opening phase (Phase 2).  

Scope of Work 

HSP planned and executed work to obtain the following:  

  1. Classification as uncategorised accommodation   
  2. Uncategorized property registration to provide hotel services  
  3. Approval of the establishment under the control of the State Sanitary Inspectorate  
  4. SANEPID Non-F&B hygienic and health registration  
  5. SANEPID- Food safety HACCAP, GMP/GHP & employees medical test  
  6. GDPR procedures to comply with data protection regulation  
  7. Low energy costs- Application to secure advantageous energy prices  
  8. Power of Attorney for GM  
  9. PKD registration for F&B and other services  

What did Hotel Solutions Partnership achieve for the client?  

HSP coordinated the numerous interdependent workstreams and sub-tasks required to achieve regulatory readiness and support a successful hotel opening.